P.K. Pujari

Revolving door

P.K. Pujari

IAS 1981, Gujarat cadre (retired Union Power Secretary)

789days after leaving Chairperson, Central Electricity Regulatory Commission (CERC). Then Adani Ports and Special Economic Zone Ltd.

The cooling-off rule

CERC term end 11 Jun 2022 to APSEZ appointment 8 Aug 2024

The rule: Electricity Act 2003 s.89(5): a CERC Chairperson or Member may not accept commercial employment for two years after leaving office; 'commercial employment' is defined by reference to organisations that were parties to proceedings before the Commission. AIS (DCRB) rule 26 (one year) applied at his 2017 superannuation from the IAS.

The gap exceeds the two-year bar in s.89(5). APSEZ is a group company of Adani Power, not itself a party in the orders listed; whether s.89(5) reaches group companies is a legal question we have not resolved. Permission: none required after two years; no record found.

Before and after

  1. Documented

    Chairperson, Central Electricity Regulatory Commission (CERC)

    Whispers in the Corridors · Adani Ports and SEZ

  2. 789 days after leaving.

  3. Documented

    Adani Ports and Special Economic Zone Ltd (APSEZ)

    Additional Director (Non-Executive, Independent), 3-year term

    appointed Dr. Ravindra Dholakia (DIN: 00069396) and Mr. P. K. Pujari (DIN: 00399995) as an Additional Directors (Non- Executive, Independent) of the Company for a term of 3 years

    APSEZ / BSE

What the office had to do with the company

  1. Petition 374/MP/2018: approved Supplemental PPAs between Gujarat Urja Vikas Nigam and Adani Power (Mundra), revising tariff after a High Power Committee report.

    When
    12 Apr 2019
    Role
    CERC (coram: P.K. Pujari, Chairperson; M.K. Iyer; I.S. Jha)
    Petition No. 374/MP/2018 Coram: Shri P. K. Pujari, Chairperson Dr. M. K. Iyer, Member Shri I.S. Jha, Member Date of Order: 12th April, 2019
    CERC, Apr 2019
    The Central Electricity Regulatory Commission (CERC) on Friday approved Adani Power's revised power purchase agreement (PPA) for its Mundra power project (4,620 Mw) with Gujarat.
    Business Standard, Apr 2019
    could allow Adani Power to hike tariffs by Rs 0.80/unit or close to a third in the current coal environment.
    Indian Express, Apr 2019
  2. Petition 251/MP/2018 (Adani Power (Mundra) v. Haryana discoms): allowed carrying cost on change-in-law compensation at the actual interest rate.

    When
    13 Jun 2019
    Role
    CERC (coram: P.K. Pujari, Chairperson; M.K. Iyer)
    Accordingly, we allow prayer of the Petitioner to claim carrying cost at the rate of actual interest rate for arranging funds (supported by Auditor’s Certificate).
    CERC, Jun 2019
  3. Review Petition 20/RP/2021 by GUVNL against an interim order in Petition 614/MP/2020 filed by Adani Power (Mundra); disposed of.

    When
    13 Dec 2021
    Role
    CERC (coram: P.K. Pujari, Chairperson; I.S. Jha; P.K. Singh)
    Coram: Shri P.K.Pujari, Chairperson Shri I.S.Jha, Member Shri P.K.Singh, Member Date of order: 13th December, 2021
    CERC, Dec 2021

What was said

No response sought by us yet; none found in coverage.

Sources

Dates and filings placed side by side; being listed is not a finding of wrongdoing. Sources were opened on Oct 2026.